Customer Adoption Roadmap

Audience: Customer's PM, sponsor, integration lead. Read with responsibilities.md (RACI per row) and ../onboarding/day-one.md (the literal Phase-1 stack-up runbook). Goal: Commercial-narrative view of the rollout in six phases. Deliverables, risks, and ownership per side.

Canonical operational sources of truth (this doc is the commercial summary; for execution detail go straight to the source): - Phase-by-phase operational plan../delivery/phased-rollout.md (eight phases, gates, acceptance criteria). - Risk register../delivery/risks.md. - RACI../delivery/stakeholders.md.


Timeline at a glance

Phase Name Duration Customer commitment
0 Discovery 1–2 weeks Sponsor + tech lead part-time
1 Local stack-up 1 day One developer, one machine
2 Customisations 2–4 weeks 1–2 developers + designer
3 Compliance / KYC / licensing 4–12 weeks Legal + compliance lead, jurisdiction-dependent
4 Pilot (closed beta) 2 weeks Ops + support + small player cohort
5 Launch 1 week Full team on-call

End-to-end best case: ~10 weeks from signature to launch (no licence delay). End-to-end realistic: ~16–20 weeks (typical jurisdiction licensing).


Phase 0 — Discovery (1–2 weeks)

Deliverables

  • Customer reads the Business track end to end.
  • Joint review of key-features.md with red/yellow/green flags against the customer's must-haves.
  • Joint review of integration-options.md — pick payment provider(s), KYC provider, social-auth strategy.
  • Gap analysis: features customer needs that Evospin doesn't ship → scoped change requests.
  • nfr-sla.md walkthrough — agree the proposed SLA tier (99.5 % vs 99.9 %) and capacity envelope.
  • Signed-off scope document.

Risks

  • Hidden requirements: jurisdiction-specific gameplay rules, currency support, or regulator-mandated audit fields surface late. Mitigation: explicit checklist in the gap-analysis worksheet.
  • Mismatch on integrations: customer expects an integration that's scaffolded (e.g. EvoGames slots, Steam OAuth) to be production-grade. Mitigation: every row in integration-options.md has an explicit maturity marker — review the maturity column in this phase.
  • SLA expectations: customer wants 99.99 %. Mitigation: surface the deployment-topology cost in this phase, not after contract.

Customer responsibilities

  • Provide must-have feature list (with priorities).
  • Identify legal jurisdiction and licensing posture.
  • Nominate technical lead, sponsor, ops lead.

ebit-team responsibilities

  • Lead doc walkthroughs.
  • Produce the gap-analysis worksheet.
  • Quote any out-of-box change requests.

Phase 1 — Local stack-up (1 day)

Deliverables

  • Customer's lead developer has the full platform running on their machine: ebit-api (port 4000), ebit-rt (4001), ebit-fe (3000), ebit-admin-fe (3001), Postgres, both Redis instances, RabbitMQ, and the full observability stack (Jaeger, Prometheus, Loki, Grafana).
  • A real bet placed via ebit-fe produces a Jaeger trace (../e2e-trace-demo.md).
  • Admin sign-in works.

Inputs / runbooks

Risks

  • Doppler access: customer can't authenticate to the dev secret store. Mitigation: plain .env template (.example.env) ships in each repo.
  • Hardware: < 8 GB RAM machine fails. Mitigation: documented in ../onboarding/day-one.md §1.

Customer responsibilities

  • Provide a developer + workstation matching prereqs.

ebit-team responsibilities

  • Pair-program through the runbook for the first developer.
  • Stand up Doppler access (if applicable).

Phase 2 — Customisations (2–4 weeks)

Deliverables

Customer-facing, per integration-options.md:

  • Brand: logo, palette, hero copy, locale set.
  • Currency catalogue + display (FX feed configured).
  • Payment provider keys (CCPayment, NowPayments, or both) wired and tested in sandbox.
  • KYC: Sumsub keys + webhook URL configured.
  • Captcha: GeeTest production keys (and reCAPTCHA fallback if used).
  • Social auth: Google / Steam keys (if in scope) — note these are scaffolded; finishing the FE flow is in scope here.
  • Game provider keys: PM8 / BGaming / Softswiss / etc. as agreed in Phase 0.
  • Observability: collector exporter pointed at customer's chosen backend (Datadog / New Relic / self-host) — config-only swap.

Risks

  • Scope creep: customer asks for new house games or new game providers mid-phase. Mitigation: every change request goes back to Phase 0 sign-off.
  • Provider sandbox lag: payment / KYC / game providers don't issue sandbox credentials inside this window. Mitigation: kick off paperwork with each external provider on day 1 of Phase 0, not Phase 2.
  • Locale gaps: copy needs translation by a third party. Mitigation: ebit-team writes EN copy; customer / their translator owns localisation.

Customer responsibilities

  • Brand assets, copy, locale translations.
  • Procure provider sandbox credentials (KYC, payments, game providers).
  • UAT each customisation as it lands.

ebit-team responsibilities

  • Apply customisations in a customer fork / branch.
  • Wire each provider integration, run end-to-end test, document any operator runbook deltas.
  • Hand over a working pre-prod build at the end of Phase 2.

Phase 3 — Compliance, KYC tier mapping, licensing (4–12 weeks, jurisdiction-dependent)

Deliverables

  • Operating licence in target jurisdiction (or partnership / sub-licence agreement).
  • Sumsub KYC tier mapping aligned to jurisdiction.
  • Country allow / deny list configured (apps/api/src/country/).
  • Responsible-gambling controls audited against jurisdiction requirements (self-exclusion, deposit / loss limits — see ⚠ TBD coverage notes in key-features.md §3).
  • Privacy notice, ToS, data controller registration.
  • Regulator filings, if any, submitted and acknowledged.

Risks

  • Licence delay: regulator response times vary widely (4–12+ weeks). Mitigation: kicked off in parallel with Phase 0; do not block Phase 1–2 on it.
  • Tier-mapping mismatch: jurisdiction requires a KYC depth Sumsub doesn't ship out-of-box. Mitigation: validated in Phase 0 gap analysis.
  • Audit log gaps: regulator requires fields Evospin doesn't currently capture. Mitigation: adds a custom column to bet, accounting, or kyc tables — scoped change in Phase 2.

Customer responsibilities

  • Own the licence application end-to-end.
  • Engage regulator and lawyers.
  • Contract Sumsub commercial relationship.
  • Operate the responsible-gambling support workflow.

ebit-team responsibilities

  • Provide audit-trail evidence (sample traces, log exports).
  • Implement any jurisdiction-specific code changes scoped in Phase 0.
  • Stay on call for technical questions from regulator's auditors.

Phase 4 — Pilot / closed beta (2 weeks)

Deliverables

  • Production deployment: HA Postgres, HA Redis, ≥2 API replicas, sticky-session rt, observability stack pointed at production OTel backend.
  • Closed cohort (1k–5k invited players) plays real money / sandboxed money depending on jurisdiction.
  • Run a stepped-ramp performance test against the production deployment (../performance-test-report.md §"How to fill this table").
  • Incident runbook validated on at least one synthetic incident (queue stuck, login failing, missing trace).
  • KPIs measured: bet success rate, payment success rate, p95 latency per endpoint class, error budget consumption.

Risks

  • Capacity surprise: production hardware behaves differently from local stack-up. Mitigation: run ../performance-testing.md protocol on the prod hardware in Phase 4.
  • External provider rate limits: payment / KYC / game providers throttle at unexpected thresholds. Mitigation: synthetic load against sandbox in Phase 2 surfaces most of this.
  • Player support volume: customer's support team is overwhelmed. Mitigation: closed-cohort sizing.

Customer responsibilities

  • Run production environment (cloud, k8s / ECS, networking, secrets).
  • Source and onboard pilot players.
  • Operate first-line support.

ebit-team responsibilities


Phase 5 — Launch (1 week)

Deliverables

  • Public open. Marketing live. Player acquisition campaigns active.
  • 24×7 on-call rota stood up (ebit-team for code-level issues, customer for ops).
  • SLA dashboard published — tracks the nfr-sla.md targets in real time on Grafana.
  • Post-launch retrospective scheduled at +14 days.

Risks

  • Traffic spike: marketing succeeds harder than predicted. Mitigation: HPA / replica scaling configured in Phase 4; capacity headroom validated under stepped ramp.
  • Compliance surprise: regulator asks for an audit log slice with zero notice. Mitigation: Loki + Jaeger retention configured in Phase 4; OTel exemplars give trace IDs per request.

Customer responsibilities

  • Own the launch.
  • Run the on-call rota.
  • Pay for production infrastructure.

ebit-team responsibilities

  • Be available for launch + hot-fix support.
  • Document any launch-week findings into ../runbooks/.